LAX People Mover faces delays with additional $400M cost

LAX People Mover faces delays with additional $400M cost
Research
Webp 8t3zoasbyvom7qhqjytuz9v5thog
Brandon Williamson Vice President Market Leader of Infrastructure/Aviation Group | AviationPros

A long-awaited Automated People Mover train at Los Angeles International Airport could finally have a set deadline for completion, with the final price tag expected to include around half a billion in legal costs.

Los Angeles World Airports staff will ask the board of commissioners on Thursday to approve $400 million more to settle claims over the delayed project at LAX, according to a board agenda released Monday. If approved, officials expect the project to finish construction on Dec. 8, 2025.

The 2.25-mile elevated train was initially supposed to be finished in 2024 ahead of the 2026 World Cup and 2028 Olympics. The train will offer a direct Metro connection and easy access to a new rental car facility and parking lot structure.

Get the Newsletter
Sign-up to receive weekly round up of news from Sky Industry News
By submitting, you agree to our Privacy Policy and Terms of Service. By providing your phone number you are opting in and consenting to receive recurring SMS/MMS messages, including automated texts, to that number from our short code. Msg & data rates may apply. Reply HELP for help, STOP to end. SMS opt-in will not be sold, rented, or shared.

The project is about 95% complete, but disagreements between the airport and contractor LAX Integrated Express Solutions (LINXS) over timeline, compensation, and production led to significant delays.

The board most recently approved an additional $200 million for the project in May to settle claims submitted by LINXS. If the board clears the way for staff to dip further into reserve funds for the airport's $30 billion overhaul—which includes a terminal and gate renumbering system, updated signage, and terminal improvements—the total settlement amount would be $550 million. That increase would also require approval from the Los Angeles City Council.

"Resolution of claims now will provide LINXS the necessary cash flow and incentive to ensure schedule certainty," the board report states.

If the allocation is cleared, the People Mover budget would increase from $2.9 billion to $3.34 billion.

Once in use, the project is expected to eliminate roughly 117,000 vehicle miles per day and carry about 30 million passengers each year. The airport saw about 75 million passengers last year.

Transit experts believe the People Mover will ease traffic at the world's fifth-busiest airport by finally offering an alternative to the airport's trafficky horseshoe loop used by hundreds of thousands of passengers each week and many of LAX's more than 50,000 employees.

This story originally appeared in Los Angeles Times.

©2024 Los Angeles Times. Visit latimes.com. Distributed by Tribune Content Agency, LLC.

###

Organizations Included in this History
More News

Airbus has released its order and delivery statistics for May, revealing that the company did not secure any new orders during the month.

Jun 9, 2025

Wizz Air is set to increase its capacity by approximately 20% in the year leading up to March 2026, despite facing challenges with a portion of its fleet being grounded due to Pratt & Whitney GTF engine issues.

Jun 9, 2025

ITA Airways is reportedly planning to expand its operations by launching over a dozen new long-haul routes in the next five years.

Jun 9, 2025

The Federal Aviation Administration (FAA) plans to suspend airline operations at Ronald Reagan Washington National Airport on the evening of June 14.

Jun 9, 2025

Wizz Air Abu Dhabi, a joint venture between Hungary-based Wizz Air and Abu Dhabi Developmental Holding Company (ADQ), has experienced significant changes since its launch in January 2021.

Jun 9, 2025

Southwest Airlines, the fourth-largest airline in the United States, has reported a total of 4,194 daily movements for June.

Jun 9, 2025