How long it takes for a new Airbus plane order to arrive

Delta Air Lines bets on ‘blended-wing’ flight to reduce emissions
Delta crash passengers should take the $30,000 payment, their lawyers say. Here’s why.
Budget airline launches new cheap flights to one of the UK’s top winter sun destinations
Brazilian airline Azul to go 'back to basics' after challenging 2024
Airlines cancel flights as air travel to ‘grind to complete halt’ this week ahead of major strike action in Europe
Dramatic moment American Airlines plane diverted to Rome is escorted by fighter jets after mid-air bomb threat
Jetstar Faces Major Backlash as Nationwide System Outage Causes Travel Chaos, Stranding Passengers and Disrupting Flights Across the Australian Airline Industry
Sudden oil supply outages creating turbulence for airline industry
Southwest's layoffs dent its worker-first culture
Abu Dhabi's long-haul carrier Etihad Airways sees record $476 million profit in 2024
Jet2 warns of profits squeeze from rising costs and late bookings
Southwest bends further to activist shareholder Elliott's demands
Downgraded on a flight? Take these simple but important steps to get your money back
Delta Offers Over $2 Million to CRJ Crash Passengers
Boeing Delays Continue for Alaska, Hawaiian
Hong Kong Airlines launches daily Sydney flights
Airline to launch new bunk beds in economy on long-haul flights next year
How Airline Employees Are Coping After Deadly Washington Crash
Major airline reverses in-flight menu change amid outcry
British Airways frequent flyer scheme changes: everything you need to know
Airline introduces world-first hand luggage ban on popular travel gadget
Air Canada Delays Boeing 767 Reentry
Flight Centre tips ‘price war’ as first direct Melbourne to LA Delta flights go on sale
FAA reverses course on meeting prohibition, blaming rogue employee
British Airways tweaks frequent flyer scheme after backlash
Delta flight from New York to Florida diverted to North Carolina due to ‘odor in the cabin’
EASA Certifies Safran’s First Electric Motor
US court blocks Biden administration's airline fee disclosure rule
JetBlue Issues Dim Outlook But Execs Remain Confident in Turnaround Plan
Delta to Resume Tel Aviv Flights April 1
How long it takes for a new Airbus plane order to arrive
Policy
Webp oi
Guillaume Faury, CEO | Airbus

When airlines announce new aircraft orders from Airbus, passengers and industry observers often wonder how long it will take before the planes are delivered and put into service. The process, however, is lengthy and complex, shaped by engineering requirements, global supply chains, and delivery logistics.

Currently, Airbus faces a backlog of about 8,000 aircraft across all models. This means that airlines placing new orders may wait several years before receiving their planes. For most commercial aircraft types, the timeline from order confirmation to delivery is typically two to three years. This period includes stages such as design finalization, material procurement, assembly, testing, and the formal handover ceremony at an Airbus delivery center. Once an aircraft reaches this stage, the handover itself takes around four to five days for inspections and documentation.

These timelines are best-case scenarios based on standard procedures without major disruptions. In reality, production delays are common due to stretched manufacturing capacity and ongoing supply chain issues. Airlines ordering popular models like the A321neo or A321XLR today might not receive them until 2028.

Get the Newsletter
Sign-up to receive weekly round up of news from Sky Industry News
By submitting, you agree to our Privacy Policy and Terms of Service. By providing your phone number you are opting in and consenting to receive recurring SMS/MMS messages, including automated texts, to that number from our short code. Msg & data rates may apply. Reply HELP for help, STOP to end. SMS opt-in will not be sold, rented, or shared.

In previous decades when Airbus had fewer orders in its backlog and lower production rates, deliveries could be completed within two years. However, as demand has increased—especially after launching programs like the A320neo in 2010—the gap between order placement and delivery has grown longer.

Several factors can affect how quickly an airline receives its aircraft. Engine shortages have become a significant bottleneck; for example, CFM International has struggled to meet demand for LEAP-1A engines used on the A320neo family. This has resulted in finished aircraft waiting for engines before they can be delivered. Customization requests from airlines also extend timelines: widebody jets with tailored cabin interiors may require additional months of work beyond standard configurations.

Other variables include certification requirements for new models (such as the A321XLR), assembly line capacity at various global sites (including Hamburg in Germany; Toulouse in France; Tianjin in China; Mobile in Alabama), and unpredictable events like geopolitical tensions or pandemics.

Airbus executives have warned customers about current delays that can reach up to three years for some narrowbody models due to high demand relative to supply. Some airline leaders have expressed frustration over these setbacks. For instance: “inexcusable,” said Flyadeal’s CEO regarding delays caused by parts shortages leaving aircraft parked in Toulouse—a concern echoed by leasing companies who note that incremental delay notifications hinder planning efforts.

To maintain schedules despite late deliveries, airlines sometimes use wet leases from third-party operators or adjust route plans—decisions that can reduce passenger options and strain relationships with manufacturers.

Comparing production strategies between Airbus and Boeing reveals differences: while both employ just-in-time manufacturing systems designed to minimize inventory costs and increase efficiency across multiple global assembly lines (for Airbus), Boeing maintains larger inventories as buffers against disruptions but faces higher costs and less geographic flexibility.

Certain exceptions exist within Airbus’ processes: widebody jets like the A350 or military variants such as the A330 MRTT follow different timelines due to complexity or specialized adaptations. During the COVID-19 pandemic, Airbus implemented virtual handovers using digital inspection tools so deliveries could continue despite travel restrictions—though some airlines were hesitant about accepting planes they had not inspected physically.

Regulatory changes also pose risks; extended certification processes for innovations such as new fuel tank systems on certain models have led to further delays.

Looking forward, Airbus aims to increase monthly output of its A320-family jets by expanding capacity at facilities including Mobile (Alabama) and Tianjin (China). The goal is to reach 75 units per month by 2027 if suppliers can keep pace—a move intended to address backlogs but still subject to external uncertainties.

For now, airlines are advised to plan conservatively around possible schedule slips while passengers should expect continued waits between order announcements and first flights aboard new aircraft.

Organizations Included in this History
More News

The International Air Transport Association (IATA) has announced that its Wings of Change Europe (WOCE) event will take place at the Steigenberger Icon Wiltcher's Hotel in Brussels.

Oct 23, 2025

Delta Air Lines has announced a new partnership with Crunchyroll, the global anime streaming platform, to bring a curated selection of anime content to its flights.

Oct 23, 2025

Delta Air Lines has been recognized as one of the 2025 Fortune Best Workplaces for Women, marking its return to the list since 2019.

Oct 23, 2025

Delta Air Lines marked its 100th anniversary by serving as the official airline of the 60th Head of the Charles Regatta (HOCR) in Boston.

Oct 23, 2025

American Airlines has announced that it will upgrade its Boeing 777-200ER aircraft with new Flagship Suites, the airline's latest business-class product.

Oct 23, 2025

Delta Air Lines will introduce a new in-flight dining partnership with Chef José Andrés, bringing Spanish-inspired cuisine to select cabins starting November 4.

Oct 23, 2025